Construction progress: February 2021

18 February 2021 1st building

Monolithic works on the first house are completed - 100%
• HVAC - 100%
Basement electrical networks:
• 1 section - 100%
• Section 2 - 96%
• Section 3 - 86%
• 4 sections - 76%
Installation of OVVK in the basement:
• 1 section - 100%
• Section 2 - 96%
• Section 3 - 71%
• Section 4 - 61%
• Installation of fire protection systems - 100%
Masonry of internal and external walls on the I house is completed:
• 1 section (commerce) - parapets - 100%
• 1 section (housing) - 1-12 floors 100%
• 2 sections - 1-10 floors - 100%
• 3 sections (housing) - 2nd and 17th floors - 100%
• 4 sections - 1-15 floors - 100%
Plastering works completed:
• 1 section (commerce) - 100% completed
• 1 section - 1-12 floors - 100%
• 2 sections - 1-10 floors - 100%
• 3 sections - 2-17 floors - 100%
• 4 sections - 2-15 floors - 100%
• Couplers of common areas - 100%
Tiles of common areas:
• 1 section - 100%
• 2 sections - 100%
• 3 sections - 96%
• Section 4 - 96%
MZK spackling:
• 1 section - 100%
• 2 sections - 100%
• Installation of railings - 96%
• Electrical networks - 100%
• Basement electrical networks of section 1 - 76%
• Installation of windows - 100%
• Installation of panoramic glazing systems:
commerce - 81%
housing - 100%
• Facade insulation - 100%
• Installation of a ventilated facade - 61%
• Waterproofing and drainage of the foundation slab - 100%
• Roof installation - 100%
• Roof waterproofing - 100%
• Laying of external water supply networks - 100%
• Laying of external sewerage networks - 100%
• Preparatory work for landscaping - 100%
• Landscaping - 28%