Construction progress: June 2021
08 June 2021 2nd building
• Monolithic works -100%
Masonry of external and internal walls: 100%
Plaster: 100%
• Electrical networks: - 80%
• Waterproofing and drainage of the foundation slab and basement walls - 100%
• Waterproofing and roof insulation - 100%
• Facade works - 60%
• Installation of windows -100%