Construction progress: December 2020

04 December 2020 2nd building

• Monolithic works -100%

Exterior wall masonry:

• 1 section - 100%

• 2nd section - 100%

• 3 sections - 1-11 floors - 100%

• 4 sections - 1-10 floors - 100%

• 5 sections - 1-11 floors - 100%

Internal walls (grooved):

• 1 section - 100%

• 2nd section - 100%

• Section 3 - 65%

• 4 sections - 75%

• Section 5 - 75%

Plaster:

• 1 section - 2-11 floors - 100%

• 2 sections - 2-10 floors - 100%

• 3 sections - 2-9 floors - 100%

• 4 sections - 2-12 floors - 100%

• Electrical networks:

• 1 section - 75%

• Section 2 - 15%

• Section 3 - 15%

• 4 sections - 15%

• Section 5 - 15%

• Waterproofing and drainage of the foundation slab and basement walls - 95%

• Waterproofing and roof insulation - 65%

• Facade works - 32%

• Installation of windows - 55%