Construction progress: December 2020
04 December 2020 2nd building
• Monolithic works -100%
Exterior wall masonry:
• 1 section - 100%
• 2nd section - 100%
• 3 sections - 1-11 floors - 100%
• 4 sections - 1-10 floors - 100%
• 5 sections - 1-11 floors - 100%
Internal walls (grooved):
• 1 section - 100%
• 2nd section - 100%
• Section 3 - 65%
• 4 sections - 75%
• Section 5 - 75%
Plaster:
• 1 section - 2-11 floors - 100%
• 2 sections - 2-10 floors - 100%
• 3 sections - 2-9 floors - 100%
• 4 sections - 2-12 floors - 100%
• Electrical networks:
• 1 section - 75%
• Section 2 - 15%
• Section 3 - 15%
• 4 sections - 15%
• Section 5 - 15%
• Waterproofing and drainage of the foundation slab and basement walls - 95%
• Waterproofing and roof insulation - 65%
• Facade works - 32%
• Installation of windows - 55%