Construction progress: December 2021

13 December 2021 2nd building

Monolithic works -100%

Masonry of external and internal walls: 100%

Plaster: 100%

• Electrical networks: - 90%

• Waterproofing and drainage of the foundation slab and basement walls - 100%

• Waterproofing and roof insulation - 100%

• Facade works - 100%

• Installation of windows -100%

Decoration of common areas:

1 section - 95%

Section 2 - 95%

Section 3 - 95%

Section 4 - 90%

Section 5 - 90%