Construction progress: December 2021
13 December 2021 2nd building
Monolithic works -100%
Masonry of external and internal walls: 100%
Plaster: 100%
• Electrical networks: - 90%
• Waterproofing and drainage of the foundation slab and basement walls - 100%
• Waterproofing and roof insulation - 100%
• Facade works - 100%
• Installation of windows -100%
Decoration of common areas:
1 section - 95%
Section 2 - 95%
Section 3 - 95%
Section 4 - 90%
Section 5 - 90%