Construction progress: February 2021
18 February 2021 2nd building
• Monolithic works -100%
Exterior wall masonry:
• 1 section - 100%
• 2nd section - 100%
• 3 sections - 1-11 floors - 100%
• 4 sections - 1-10 floors - 100%
• 5 sections - 1-11 floors - 100%
Internal walls (grooved):
• 1 section - 100%
• 2nd section - 100%
• Section 3 -78%
• Section 4 - 83%
• Section 5 - 83%
Plaster:
• 1 section - 2-11 floors - 100%
• 2 sections - 2-10 floors - 100%
• 3 sections - 2-9 floors - 100%
• 4 sections - 2-12 floors - 100%
• Electrical networks:
• 1 section - 90%
• Section 2 - 31%
• Section 3 - 31%
• Section 4 - 31%
• Section 5 - 31%
• Waterproofing and drainage of the foundation slab and basement walls - 98%
• Waterproofing and roof insulation - 90%
• Facade works - 37%
• Installation of windows - 70%