Construction progress: August 2021
16 August 2021 2nd building
• Monolithic works -100%
Masonry of external and internal walls: 100%
Plaster: 100%
• Electrical networks: - 85%
• Waterproofing and drainage of the foundation slab and basement walls - 100%
• Waterproofing and roof insulation - 100%
• Facade works - 80%
• Installation of windows -100%
Decoration of common areas:
1 section - 20%
Section 2 - 15%
Section 3 - 10%
Section 4 - 10%