Construction progress: January 2021
14 January 2021 2nd building
• Monolithic works -100%
Exterior wall masonry:
• 1 section - 100%
• 2nd section - 100%
• 3 sections - 1-11 floors - 100%
• 4 sections - 1-10 floors - 100%
• 5 sections - 1-11 floors - 100%
Internal walls (grooved):
• 1 section - 100%
• 2nd section - 100%
• Section 3 -75%
• 4 sections - 80%
• Section 5 - 80%
Plaster:
• 1 section - 2-11 floors - 100%
• 2 sections - 2-10 floors - 100%
• 3 sections - 2-9 floors - 100%
• 4 sections - 2-12 floors - 100%
• Electrical networks:
• 1 section - 85%
• Section 2 - 25%
• Section 3 - 25%
• 4 sections - 25%
• Section 5 - 25%
• Waterproofing and drainage of the foundation slab and basement walls - 95%
• Waterproofing and roof insulation - 85%
• Facade works - 32% • Installation of windows - 65%