Construction progress: May 2021
14 May 2021 2nd building
• Monolithic works -100%
Exterior wall masonry:
• 1 section - 100%
• 2nd section - 100%
• 3 sections - 1-11 floors - 100%
• 4 sections - 1-10 floors - 100%
• 5 sections - 1-11 floors - 100%
Internal walls (grooved):
• 1 section - 100%
• 2nd section - 100%
• Section 3 -90%
• 4 sections - 90%
• Section 5 - 90%
Plaster:
• 1 section - 2-11 floors - 100%
• 2 sections - 2-10 floors - 100%
• 3 sections - 2-9 floors - 100%
• 4 sections - 2-12 floors - 100%
• Electrical networks:
• 1 section - 98%
• Section 2 - 45%
• Section 3 - 45%
• 4 sections - 45%
• Section 5 - 45%
• Waterproofing and drainage of the foundation slab and basement walls - 98%
• Waterproofing and roof insulation - 95%
• Facade works - 55%
• Installation of windows - 80%