Construction progress: October 2021

19 October 2021 2nd building

• Monolithic works -100%
Masonry of external and internal walls of 100%
100% plaster
• Electrical networks: - 90%
• Waterproofing and drainage of the foundation slab and basement walls-100%
• Waterproofing and roof insulation - 100%
• Facade works - 100%
• Installation of windows -100%
Decoration of common areas:
1 section - 50%
Section 2 - 50%
Section 3 - 40%
Section 4 - 30%
Section 5 - 30%