Construction progress: March 2022
31 March 2022 3rd building
Monolithic works in 3 houses - completed:
• 1 section - 100%
• Section 2 - 100%
• 3 sections - 100%
Masonry of external and internal walls in 3 houses - completed:
• 1 section - 100%
• Section 2 - 100%
• 3 sections - 100%
Window installation - completed:
• 1 section - 100%
• Section 2 - 100%
- 3 sections - 100%
Facade works:
• 1 section - 70%
• Section 2 - 20%
Distribution of water, heating, sewerage per apartment and in MZK:
• 1 section - 90%
• Section 2 - 30%
Plaster works -
• 1 section - 100%
• Section 2 - 50%
• Section 3 - 30%
MZK decoration
• 1 section - 20%
MZK screed
• 1 section - 100%
Installation of entrance doors apartment by apartment:
• 1 section - 100%