Construction progress: June 2021

08 June 2021 3rd building

• Monolithic works:
• 1 section - 95%
• Section 2 - 85%
• Section 3 - 50%
Laying of external and Internal walls (ceramic block, brick, groove):
• 1 section - 40%
• Section 2 - 40%
• Section 3 -15%