Construction progress: December 2021

13 December 2021 3rd building

Monolithic works:

• 1 section - 100%

• Section 2 - 100%

• 3 sections - 100%

Laying external and internal walls (ceramic block, brick, groove):

• 1 section - 100%

• Section 2 - 95%

• 3 sections - 50%

Installation of windows:

• 1 section - 100%

• Section 2 - 90%