Construction progress: December 2021
13 December 2021 3rd building
Monolithic works:
• 1 section - 100%
• Section 2 - 100%
• 3 sections - 100%
Laying external and internal walls (ceramic block, brick, groove):
• 1 section - 100%
• Section 2 - 95%
• 3 sections - 50%
Installation of windows:
• 1 section - 100%
• Section 2 - 90%