Construction progress: April 2021

08 April 2021 3rd building

• Monolithic works:
• 1 section - 80%
• Section 2 - 70%
• 3 sections - 1-10 floors - 20%
Internal walls (grooved):
• 1 section - 20%
• Section 2 - 20%
• 3 sections –10%