Construction progress: July 2021

14 July 2021 3rd building

• Monolithic works:
• 1 section - 99%
• Section 2 - 90%
• Section 3 - 80%
Laying of external and Internal walls (ceramic block, brick, groove):
• 1 section - 80%
• Section 2 - 50%
• Section 3 -15%