Construction progress: November 2021
17 November 2021 3rd building
Monolithic works:
• 1 section - 100%
• 2nd section - 100%
• 3 sections - 100%
Masonry exterior and interior walls (ceramic block, brick, groove):
• 1 section - 100%
• Section 2 - 85%
• Section 3 -35%
Installation of windows:
• 1 section - 100%
• Section 2 - 60%