Construction progress: February 2022

11 February 2022 3rd building

Monolithic works in 3 houses - completed:
• 1 section - 100%
• Section 2 - 100%
• 3 sections - 100%
Masonry of external and internal walls in 3 houses - final:
• 1 section - 100%
• Section 2 - 100%
• 3 sections - 100%
Plaster works -
• 1 section - 100%
Strainer
• 1 section - 100%
Installation of windows:
• 1 section - 100%
• Section 2 - 90%
- 3 sections - 50%
Facade works:
• 1 section - 50%