Construction progress: August 2021

16 August 2021 3rd building

• Monolithic works:
• 1 section - 100%
• Section 2 - 95%
• Section 3 - 90%
Masonry exterior and interior walls (ceramic block, brick, groove):
• 1 section - 95%
• Section 2 - 60%
• Section 3 -15%