Construction progress: September 2021

09 September 2021 3rd building

• Monolithic works:
• 1 section - 100%
• 2nd section - 100%
• Section 3 - 95%
Masonry exterior and interior walls (ceramic block, brick, groove):
• 1 section - 97%
• Section 2 - 65%
• 3 sections –20%